Sidewalk Access to Meyer Hall Limited During Construction

Due to the sidewalk construction project, access to Meyer Hall currently is limited to the ADA-accessible ramp leading towards the Centennial Center.

Weather permitting, construction of the sidewalk east of Meyer Hall and the storm sewer work between Meyer Hall and the Centennial Center is expected to be completed before May 6 (commencement weekend).

Following completion at those two sites, work will begin on removing the old steam tunnel between Meyer Hall and Prep Hall. Afterwards, the contractor will replace the sidewalks between the Centennial Center and the Prep Hall parking lot. The project will conclude with replacement of the Prep Hall parking lot. These portions of the construction project are scheduled to begin after commencement weekend and be completed by June 30.

University officials thank members of the campus community for their continued patience during this construction project.